Jump to content Jump to navigation Jump to search

Replacewithtranslations
Global
Replacewithtranslations
Albania
Replacewithtranslations
Brazil
Replacewithtranslations
Chile
Replacewithtranslations
France
Replacewithtranslations
Germany
Replacewithtranslations
India
Replacewithtranslations
Ireland
Replacewithtranslations
Netherlands
Replacewithtranslations
Norway
Replacewithtranslations
Peru
Replacewithtranslations
Spain
Replacewithtranslations
Sweden
Replacewithtranslations
Turkey
Replacewithtranslations
United Kingdom
Replacewithtranslations
United States

Moglicë HPP tests continue

13 Apr, 2020

The start of 2020 marked the beginning of the testing phase for Moglicë Hydropower Plant, the largest HPP of the Devoll Hydropower Project, a Statkraft investment in Albania

After several years in development and implementation, during 2019 were completed the main works and started the creation of the Moglice reservoir.

The largest private hydropower plant in Albania during these months has undergone a series of tests to commission and prepare it for operations. These are carried out by specialised companies in coordination with the structures of the Ministry of Infrastructure and Energy.

In the frame of this phase, on 12.04.2020 was carried out the test of the Moglice Dam Spillway gates, which resulted successful. Full commercial operations for the Moglice HPP are planned for the second quarter of 2020, even with the additional difficulties due to the Covid-19 pandemic.