Countries

Global flag icon
Global
Albania flag icon
Albania
Brazil flag icon
Brazil
Chile flag icon
Chile
Finland flag icon
Finland
France flag icon
France
Germany flag icon
Germany
India flag icon
India
Ireland flag icon
Ireland
Italy flag icon
Italy
Netherlands flag icon
Netherlands
Norway flag icon
Norway
Peru flag icon
Peru
Spain flag icon
Spain
Sweden flag icon
Sweden
Turkey flag icon
Turkey
United Kingdom flag icon
United Kingdom
United States flag icon
United States

Energy Isles, Tittyans Hill

Welcome to the Knockcronal Wind Farm project page

Welcome to our dedicated website for Knockcronal Wind Farm.

Following thorough site surveys and two public consultation events undertaken in May and September 2021, we submitted Knockcronal Wind Farm’s planning application to the Scottish Government’s Energy Consents Unit (ECU) at the end of November 2021.

The planning application consists of 6 turbines up to 200 m blade tip height and 3 turbines up to 180 m blade tip height, with an expected installed capacity of approximately 59.4 MW. The planning application also seeks consent for energy storage opportunities onsite as well.

We would like to thank everyone who has taken the time to provide their views on the proposal and help shape the project.

In light of the current Covid-19 restrictions the planning documents are available to view online. You can access the documents at the ECU's website under the application reference ECU00002181. We have also uploaded the documents on our project website.

This website will be kept updated to keep you informed of how the project progresses through the planning process.

Please complete the feedback form to share your views, or ask a question.

We are following all Scottish Government advice in relation to Covid-19 as we progress our plans.

 

Landscape and Visual Presentation

How have we considered the landscape and surrounding area as we have developed the project? Project Manager John Wallace explains.

  • Stage 1: Site Selection (12 months)

    Extensive research to identify suitable sites: positive indicators include good wind speed and minimal environmental and technical constraints. 

     

  • Stage 2: Pre-Planning (6 - 12 months)

    We request the view of the Scottish Government and South Ayrshire Council on the level of study required (known as "Scoping") to assess the proposal. 

     

     

  • Stage 3: Submit Planning Application, and Decision (12 months)

    An application is submitted to the Scottish Government, accompanied by a comprehensive Environmental Report showing the results of all studies undertaken.  

     

  • Stage 4: Construction (12 - 18 months)

    If Knockcronal Wind Farm is approved, construction begins at least one year after consent.

     

  • Stage 5: Operation (30-35 years)

    The turbines are managed from a regionally based maintenance team, and operations are controlled by detailed planning conditions.

     

  • Stage 6: Decommissioning (12 months)

    At the end of the planning period, turbines are removed. A financial bond or parent company guarantee is put in place before construction starts to cover this cost.

     

Articles

Find your frequently asked questions here

If you cant find your quesion here, please leave us your question in the form on the bottom of the page and we will give you an answer as soon as we can.  

Read more

Local Suppliers

Our aim is to have the least impact and provide the most benefit to the communities in which we operate. The construction phase is one way we can create economic benefits through inward investment, a...

Read more

The project team

John Wallace
Project Manager
Harry Handford
Project Manager
Ruth Semple
Community Liaison Manager

Member of

Scottish renewables-2.png 2022-06-22 13_28_37-Window.jpg

Learn more about Statkraft and wind power

The history of Statkraft

A short animated video of the History of Statkraft

Statkrafts history

A deep dive into the vast 125 years of history as Europe's largest renewable energy producer.

Wind power - how does it work?

Learn how wind power is generating power.

Did you find what you were looking for?